Version: 1.0 2005-02-08 Gaspare Lo Curto
Version: 1.1 2005-10-18 Gaspare Lo Curto
Version: 1.2 2005-11-28 Gaspare Lo Curto

NEWS

Commissioning plan updated, including scientific commissioning plan: 28-11-2005.

Introduction

The "High efficiency mode" upgrade of HARPS was first foreseen during the second Instrument Science Team meeting held on May 8, 2002 at the Observatiore de Geneve.
The final version of the User Requirement document was prepared on March 5, 2004.
The Preliminary Design Review was held on La Silla with videolink to Geneva and Garching on July 15th 2004. The reviewer was Francesco Pepe from ODG. The reviewer recommended to continue the project with a list of actions. This project was inserted in the La Silla SciOps G&O for 2005 by the LSO Director. On 18-01-2005 the LSO management finally gave green light to continue the project.
On May 13th, 2005 the project passed the Final Design Review and entered in the production stage.

Available documents:

Reference documents

IST meeting recommending EGGS 3M6-MIN-ESO-33100-0009 22-07-2002 postscript
User requirements 3M6-SPE-ESO-13100-0012 05-03-2004 postscript, PDF
PDR document 3P6-TRE-ESO-70200-0001 12-07-2004 DOC
Minutes of PDR and reviewer comments 3M6-MIN-HAR-33100-0031 23-08-2004 HTML
Answers to reviewer general comments 3M6-MIN-HAR-33100-0031 appendix 23-08-2004 HTML
05-04-2005 Viedo conference minutes 3P6-MIN-ESO-90400-0001 06-04-2005 PDF
 
Final Design Review documents

Fiber splicing test INS-04/17 05-10-2004 DOC
Harps High Efficiency Fiber shutter electronics design 3P6-DSD-ESO-60400-0002 15-05-2005 PDF
HARPS High Efficiency Mode Software design 3P6-SDS-ESO-80030-0005 14-05-2005 PDF
HARPS High Efficiency Fiber Head Opto-Mechanical design 3P6-DSD-ESO-754-0001 04-05-2005 PDF
Appendix to the Opto-Mechanical design 06-05-2005 PDF
HARPS High Efficiency Mode Project Plan 3P6-PLA-ESO-60400-0002 13-05-2005 PDF
EGGS commissioning plan. 3P6-PLA-ESO-90400-0002V1.2 28-11-2005 PDF
 
Form for RIX submission

RIX form 03-05-2005 EXCEL
 
All RIX with answers and conclusions by reviewers.

EGGS RIX Collection 12-05-2005 EXCEL, PDF

Reviewers recommendations and action points. 18-05-2005 ASCII
 
 
Additional documents.

EGGS Mode Data Interface Control Document 3P6-SDS-ESO-90030-0007 15-05-2005 PDF
 
 
Technical commissioning.

Individual night reports ASCII
Technical Commissioning report 3P6-TRE-ESO-90200-0007 13-09-2005 PDF




Milestones



Final design review passed with actions 13-05-2005
Technical commissioning17/19-07-2005
Scientific commissioning12/15-12-2005



Acronyms

EGGS: Extra Good General Spectroscopy, to be distinguished from
HAM : High Accuracy Mode