EGGS FDR conclusions (by F. Pepe, on behalf of the Review Board) ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ General comments ---------------- The Review Board composed of F. Pepe (OG, chairman), G. Rupprecht, B. Buzzoni (ESO Garching), Gerardo Ihle, Ismo Kastynen, and Augustin Macchino (ESO La Silla) has received by May 5th, 2005 the full documentation related to the final design review of EGGS, the new high-efficiency mode of HARPS. This documentation has been reviewed and RIX have been issued by the Board. The RIXs have been answered by the EGGS Project members by May 12th. The Review took finally place by videoconference on May 13th, 2005 at 16 pm CET. The review board considers that: A) The open questions raised during the previous review in autumn 2005 have been addressed in a satisfactory way and that no critical item was left undiscussed. B) The presented documentation was comprehensive, complete and clear. C) The conditions were fulfilled to carry out the final design review. Review status ------------- After analysis of the documentation and discussion of the RIX the Review Board declares the Review "successfully passed with action items". A list of action items and recommendations have been issued and is presented below. The Review Board presents his compliments and his best wishes to the project and its members. Recommendations --------------- The Review Board recommends the project members to: 1) Analyze the actions and execute them carefully in short delay, at latest at the defined deadline. 2) Keep the template and instrument mode names for the "old" mode (high accuracy mode) unchanged - as also strongly recommended by ESO's DMD. 3) Proceed with the implementation of EGGS with highest priority in order to have first light before ESO's Call for Proposal (End of August 2005), and therefore to tightly follow-up the project tasks and the tight schedule. 4) Propose a back-up plan for the case of the foreseen schedule, and in particular the Technical Commissioning date, could not be kept. 5) Ensure in any project phase the "health" of the standard high-accuracy mode and its operations. Action Items ++++++++++++ Action Item Nr.: 1 Responsible(s): Gilliotte, Avila Action: Update the Alignment Procedure considering all the comments made in the RIXs. Deadline: 27/05/2005 Action Item Nr.: 2 Responsible(s): Alonso, Eckert Action: Investigate the possibility of manufacturing a spare plane blade with holes, and if possible, manufacture it. Deadline: Technical Commissioning Action Item Nr.: 3 Responsible(s): Alonso, Eckert, Avila, Gilliotte Action: Include in the mechanical design a protection (cylinder) for the rod lens which can be ideally used also as mounting and alignment tool. Deadline: 27/05/2005 Action Item Nr.: 4 Responsible(s): Avila, Gilliotte Action: Prepare a detailed AIV (Assembly, Integration and Verification) and Alignment Plan. Include a list of tasks, sequencing and scheduling. Consider and plan also interventions on the instrument and the telescope. Include also the verification of the fiber-head efficiency (complete fiber head with spliced fibers). Deadline: 15/06/2005 Action Item Nr.: 5 Responsible(s): Tzu-Chiang Shen Action: Prepare an SW ICD (Interface Control Document) to be submitted at DICB and OG for approval. This ICD must include the description of the new Keywords, of the changes in OS/ICS, as well as the description of the new templates. After approval by DICB and OG, update correspondingly the HARPS Dictionary, the OS/ICS manual, and the Template Reference guide. Deadline: Technical Commissioning Action Item Nr.: 6 Responsible(s): Lo Curto Action: Propose a back-up plan for the case of the foreseen schedule, and in particular the Technical Commissioning date, could not be kept. Deadline: 27/05/2005 Action Item Nr.: 7 Responsible(s): Lo Curto Action: As soon as the ICD has been issued and accepted (AI5), organize and plan the modifications to STS, Trigger and DRS in more detail. To be done in collaboration with OG. Also include a verification plan (what to be verified on technical frames) and elaborate further the Commissioning Plan). Deadline: Technical Commissioning + 2 weeks Action Item Nr.: 8 Responsible(s): Lo Curto Action: Prepare a Calibration and Operation Plan for the EGGS mode. In particular consider the mixed operation aspects with HAM. Deadline: Scientific Commissioning