Last update of this page: Wed Oct 7 15:41:04 2009
Run State: COMPLETED
USD review status:
O.K.!
| Pre-Imaging? | Special-Calibration? | Time-Critical? | ToO/GTO/Large program? | Carry-Over? | |
|---|---|---|---|---|---|
|
Special Remarks:
OBs for each target should be completed within a single night!
Abstract for MTS:
This is a FLAMES/Giraffe program on a RSG population in 2 galactic clusters.
The PI asks to complete the OBs for one single cluster on the same night. This should be no problem for RSGC2, which has only 2 OBs, one hour each. More cumbersome is the case of RSGC3, for which 4 OBs, one hour each, have been submitted.
The PI is aware that, especially for the second case, this will be attempted on a best effort basis.
If it is not possible to complete one object in one single night, please try to complete it on the following night. If this turns out to be impossible, then contact usd-help@eso.org
README of this run:
Web version of approved README readme_81034600.html