Last update of this page: Wed Oct 7 15:41:04 2009
Run State: COMPLETED
USD review status:
O.K.!
| Pre-Imaging? | Special-Calibration? | Time-Critical? | ToO/GTO/Large program? | Carry-Over? | ||
|---|---|---|---|---|---|---|
|
|
Special Remarks:
URGENT: TO BE EXECUTED AS SOON AS POSSIBLE AT VERY BEGINNING OF NIGHT
Abstract for MTS:
Programme consists of two runs (A and B), one 1h OB each.
Run A has already been executed in early Nov 2007.
This run (run B) must be executed and completed between Jan 10 and 20, with
the optimal observing date being the night of Jan 15.
No other requirements.
README of this run:
Web version of approved README readme_80501101.html