Last update of this page: Thu Jan 29 15:41:32 2009
Run State: COMPLETED
USD review status:
O.K.!
| Pre-Imaging? | Special-Calibration? | Time-Critical? | ToO/GTO/Large program? | Carry-Over? |
|---|---|---|---|---|
Special Remarks:
OBs must be executed in pairs across 6 nights with specific time spacings.
Abstract for MTS:
This is a FLAME/COM8 programme on binary stars in a GC.
NOTE (23/07/2007): there are two OBs left. Execute them on a random epoch whenever the conditions are suitable.
---------------------------------------
The programme is split into three runs:
A) OBs must be executed within 6 nights. Once the first observations are done
on the first night, indicated as "reference epoch" (OBs xxx_night1_A + xxx_night1_B), the remaing groups of _A,_B OBs have to be executed 1, 3 and 5 nights after the first epoch.
For each night, OBs _A and _B have to be executed one after the other.
Ideally, the reference epoch should be taken around end of May 2007.
B) includes two OBs (xxx_night5_A, xxx_night5_B), to be executed 20 days after
the reference epoch.
C) includes two OBs (xxx_night6_A, xxx_night5_6), to be executed 90 days after
the reference epoch.
Note that the programme should be executed under the specified conditions. Nevertheless, since it is also time critical, the PI asks to relax the constraints
to seeing<=1.2, FLI=1.0 and THN conditions.
README of this run:
Web version of approved README readme_79067400.html