EUROPEAN SOUTHERN OBSERVATORY
La Silla - Science Operation Department
FEROS on the MPG/ESO-2.20m
Version: 1.0 2005-03-28 J.D.Pritchard
Highlights of the Commissioning of the FEROS ADC at the ESO/MPI 2.2m telescope
Commissioning I
-- September 21 - October 17, 1998
Commissioning II
-- November 11 - 30, 1998
Commissioning III
-- October 22/23 - 25/26 2002
Commissioning IV
-- November 13/14 - 14/15 2002
Commissioning V
-- March 08/09 - 10/11 2003
Commissioning VI
-- October 09/10 - 14/15 2003
Commissioning VII
-- November 10/11 - 15/16 2003
Summary
The FEROS-II (aka FEROS BigBang) Project was a resounding success.
Commissioning VI -- October 09/10 - 14/15 2003
This commissioning is focussed on the technical verification of the new VLTSW based systems.
Commissioning VII -- November 10/11 - 15/16 2003
This commissioning is focussed on the scientific verification of the new VLTSW based systems.
Last revision: J.D.Pritchard 2003-03-28
Comments
[
ESO
|
LaSilla
|
SciOp
]