Generated by ARS on 7/5/2005 2:28:44 PM ACTION ITEMS LIST FOR SUPPORT TEAMS AND LOGISTIC Telescope : REM Create-date : 6/21/2005 2:39:42 PM Problem Short Description : Crycoolers are not providing the requested temperature. Action : Replace crycooler by LN2 system. Action Log : 6/28/2005 4:55:44 PM gandreon Question: who is going to refill the dewar? 7/5/2005 2:25:52 PM gandreon in progress Responsible : Engineering (Mechanics) Status : Assigned Deadline : 7/31/2005 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : REM Create-date : 7/5/2005 2:25:16 PM Problem Short Description : GPS is damaged. Action : Replace equipment, antenna, and cable. Action Log : Responsible : Engineering (Electronics) Status : Assigned Deadline : 7/31/2005 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO NTT Create-date : 5/2/2005 4:50:05 PM Problem Short Description : If one needs to see the telemetry values of EMMI blue ccd, it is necessay to look directly to the PULPO's display. Action : Connect the pulpo to the serial port of LEMCB and implement remote monitoring adding points in DB. Action Log : 5/3/2005 3:16:12 PM gandreon Please analyze the problem and report. 5/25/2005 9:24:09 AM gandreon JRE working in the software. 7/3/2005 2:31:13 PM jreveco The software is ready for tests. Currently, the LCU can't get connected to PULPO, but it could be a problem of the serial cable. As soon as the priorities of the Deep Impact ends, the cable will be checked. Responsible : Engineering (Software) Status : Assigned Deadline : 7/31/2005 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO NTT Create-date : 6/14/2005 2:49:14 PM Problem Short Description : Increase between 3 and 10 times the efficiency of the calibration lamp for EMMI in echelle mode Action : Locate, procure, install, and test a different type of calibration lamp. Action Log : 6/20/2005 9:49:37 AM agilliot The new lamp type is requested to Paranal for a test, if spare exists. 7/5/2005 2:26:11 PM gandreon No answer yet. Responsible : Engineering (Instrum.) Status : Assigned Deadline : Deadline Status : Not Assigned ________________________________________________________________________________ Telescope : ESO NTT Create-date : 6/21/2005 2:42:17 PM Problem Short Description : A special filter ir required for EMMI Action : Design and manufacture a special support Action Log : Responsible : Engineering (Instrum.) Status : Closed Deadline : 6/29/2005 12:00:00 AM Deadline Status : Closed on Time ________________________________________________________________________________ Telescope : ESO 360 Create-date : 6/21/2005 2:40:51 PM Problem Short Description : Info on ADC is not provided for CES Action : Please provide the same panel developed for HARPS, including Alfa and Delta coordinates Action Log : 7/5/2005 8:55:38 AM tshen Done. Waiting for commissioning. Responsible : Engineering (Software) Status : Completed Deadline : 7/5/2005 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : SAFETY Create-date : 5/3/2005 3:13:13 PM Problem Short Description : Fire alarm is not detected directly from people at Ritz. Action : Add audible and visible signaling for alarms triggered in Ritz, 360, 220, ntt, and danish 154. Action Log : 5/10/2005 2:51:54 PM gandreon Written requirements will be circulated by Safety Engineer for review, followed by an implementation plan. 5/25/2005 9:27:10 AM gandreon Waiting for comments to distributed User requirements 5/31/2005 2:39:14 PM gandreon Comments have been received and they will be taken into account in the second release of the requirements. Responsible : Infrastructure Support Group Status : Assigned Deadline : Deadline Status : Not Assigned ________________________________________________________________________________ Telescope : SAFETY Create-date : 6/8/2005 3:30:00 PM Problem Short Description : UPS Rooms require fire extinguishers Action : To install the fire extinguisher holders in a place determined by the safety engineer. To clearly mark the presence of these implements. Action Log : 6/21/2005 2:47:01 PM gandreon Support ordered. They should arrive this Friday. Responsible : Logistics(Site Maint.) Status : Assigned Deadline : 7/5/2005 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : RITZ Create-date : 6/21/2005 2:43:19 PM Problem Short Description : Insufficient illumination on some desks Action : Install new lamps hanging from the ceiling Action Log : Responsible : Logistics(Site Maint.) Status : Assigned Deadline : Deadline Status : Not Assigned ________________________________________________________________________________ Telescope : GENERAL Create-date : 6/21/2005 2:44:31 PM Problem Short Description : Some electrical panels use obsolate fuses for which no spare is available. Action : First suggest a replacement. Action Log : 6/28/2005 4:56:56 PM gandreon Luis will comment on this request. 7/5/2005 2:28:18 PM gandreon Waiting for report from Luis Aguila Responsible : Infrastructure Support Group Status : New Deadline : Deadline Status : Not Assigned ________________________________________________________________________________ Telescope : GENERAL Create-date : 6/28/2005 4:54:21 PM Problem Short Description : The new CNC requires a network connection. Action : Please install an access point after providing a temporary connection for the start of operations. Action Log : Responsible : Software&Commun.Supp.T. Status : Assigned Deadline : Deadline Status : Not Assigned ________________________________________________________________________________