Generated by ARS on 8/17/01 8:40:48 AM ACTION ITEMS LIST FOR SUPPORT TEAMS AND LOGISTIC Telescope : ESO NTT Create-date : 6/21/01 3:27:57 PM Problem Short Description : Flexure template requires more streamlining in internal communication. Action : tif modification to enable the rotational control from wemmi for rotators A and B, and from wsofi to rotator A. Action Log : 7/19/01 2:57:13 PM gandreon Ther will be one week delay. 8/2/01 2:52:37 PM gandreon Manpower planned for this action had to be diverted to 220 upgrade for the family problem of one programmer. 8/9/01 4:46:01 PM gandreon New deadline agreed. 8/9/01 4:47:17 PM gandreon Scope also enlarged to wsofi. Responsible : Software&Commun.Supp.T. Status : Assigned Deadline : 8/20/01 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO NTT Create-date : 6/26/01 9:00:11 PM Problem Short Description : No restriction currently exists on access to NTT computer systems. Action : An access list should be included in the NTT router. Action Log : 6/28/01 3:09:59 PM gandreon Provisonal access list: wlsops1, wlsops2, DFS systems. 7/19/01 2:58:27 PM gandreon The router with new restriction is ready and it will be installed next week. 7/26/01 2:47:44 PM gihle MPA will check the installation during this week end. Detectors asked to add subnets 124, 128 to 255 to the list. 8/2/01 2:53:34 PM gandreon IPs of specific systems have replaced the subnets. Responsible : Software&Commun.Supp.T. Status : Closed Deadline : 7/4/01 11:00:00 PM Deadline Status : Closed on Time ________________________________________________________________________________ Telescope : ESO NTT Create-date : 7/1/01 11:34:24 AM Problem Short Description : LAN still slow Action : Router exchange (one interface suspicious) and reconfiguration of gigabit switch will be done. Action Log : 7/5/01 2:43:52 PM gandreon TT should provide the names of a couple of systems (une client and one server) to be used as reference. Then, SWC will check the system configurations, the routing, and perform any other test necessary to devise a solution. If the bottleneck will be located in the router to the backbone, a purchase of a different model will be considered (if justified). 7/26/01 2:48:37 PM gihle MPA will make the study and will determine the deadline. 8/2/01 2:55:37 PM gandreon Configuration of router's interfaces have been modified. More actions to come. 8/9/01 4:48:29 PM gandreon Investigation to be extended to data storage systems. Responsible : Software&Commun.Supp.T. Status : Assigned Deadline : 9/1/01 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO NTT Create-date : 7/18/01 4:11:55 PM Problem Short Description : The old electronic box used to measure the EMMI ccd's vacuum is getting aged. No spare available. Action : Make possible the reading of EMI ccd's vacuum by Pulpo (sensor has to be changed). Action Log : 7/26/01 2:51:51 PM gihle New sensors have to be purchased. First a price inquire is required. Time being 2nd hand sensors are going to be installed. Due to this problems PLE (NTT Team) proposed a one month delay in the deadline. 8/2/01 2:57:14 PM gandreon PR has been sent for more sensors. One working spare will be installed in EMMI red in the meantime. 8/9/01 4:48:54 PM gandreon PR has been issued. Responsible : Instrumentation Support Team Status : Assigned Deadline : 9/13/01 11:00:00 PM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO NTT Create-date : 7/18/01 6:48:45 PM Problem Short Description : N2 bottle transfer pipes : Pressure gauge fails too often due to knocks needed for tightening "transfer sealing fastener" Action : N2 bottle-transfer_pipe junction system should be improved in order not to need anymore hitting the unit. Action Log : 8/2/01 2:58:04 PM gandreon L Gonzales is in sick leave. Deadline will be assigned when he resumes service. Responsible : Mechanics Support Team Status : Assigned Deadline : Deadline Status : Not Assigned ________________________________________________________________________________ Telescope : ESO NTT Create-date : 7/18/01 6:55:11 PM Problem Short Description : sometimes there is no time to wait for N2 bottles to get full pressure. Action : Install the - already tested - pressurizer prototype on all the N2 transfer pipes used by NTTT. Action Log : Responsible : Mechanics Support Team Status : Assigned Deadline : Deadline Status : Not Assigned ________________________________________________________________________________ Telescope : ESO NTT Create-date : 7/19/01 2:53:00 PM Problem Short Description : Refilling water tanks of humidifier is an heavy burden. Action : A central tank could be filled directly from the truck and then water distributed to humidifiers. Action Log : 7/26/01 2:53:21 PM gihle A project was presented by ISG. However, it was decided to study such a change in relation to the future new NTT offices. 8/2/01 3:01:59 PM gandreon The plan for a small project is ready. While this project is undertaken, the safety engineer will provide asap all TTeams with smaller containers for conformance to safety measures. Responsible : Infrastructure Support Group Status : Closed Deadline : Deadline Status : Closed on Time ________________________________________________________________________________ Telescope : ESO NTT Create-date : 7/19/01 2:54:30 PM Problem Short Description : Trolleys used for M1 removal are an heavy load for the building. Action : Prepare a roofed protection on the upper platform for they storage. Point subject to Director's approval. Action Log : 7/26/01 3:00:35 PM gihle A project was presented by ISG. A discussion regarding the inconveniences to install the protection outside the building came in the meeting. 8/2/01 3:03:33 PM gandreon An alternative option is the storage in the 360 ground floor. To be approved by LSO Director. 8/2/01 3:40:49 PM gandreon Approved by Director. 8/16/01 3:02:12 PM gandreon Back to assigned! Just do it! 8/16/01 3:02:49 PM gandreon Correction: just have it done by mechanics! Responsible : Infrastructure Support Group Status : Assigned Deadline : 8/2/01 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO 360 Create-date : 12/30/99 1:14:33 PM Problem Short Description : Tube against parasitic light for CES Very Long Camera Action : A tube is required for the CES VLC to baffle straylight. As was present with the old Long Camera a tube is required that contains the camera mirror and extends beyond the folding mirror to baffle light. It needs to have a provision for easy access to the Hartmann mask such as a slidable door, or equivalent. Action Log : 1/13/00 2:26:57 PM gandreon More analisys is required. Tube may not be the best solution and it will be an heavy job. Currently the main source of parassitic light seems to have been cut (all LEDs off in Fiera). 2/3/00 4:43:18 PM gandreon Tests performed by R Tighe were satisfactory. To be confirmed by Martin. 2/10/00 5:22:45 PM gandreon A temporary solution has reduced parassitic light by a factor of 9. Therefore a permanent one should be devised. Deadline to be negotiated. 3/2/00 2:51:58 PM gandreon Proposal is for end of April. 3/9/00 4:26:07 PM gandreon Design ready. To be approved by Martin Kuster. 3/16/00 3:08:31 PM gandreon One source of light has been descovered and eliminated shoielding the fiber carrying data to/from Fiera. Action on hold unitl confirmed by Martin that now there is no more parassitic light. 4/6/00 3:29:52 PM gandreon Two protections have to be built, one for 45 degrees mirror and one for the grating. Deadline changed by the Director. 10/26/00 2:33:54 PM gandreon One ready. One nearly ready. 10/31/00 1:21:08 PM gihle Protection was installed. 11/16/00 2:17:15 PM gandreon It will be completed during next turno. 11/28/00 4:39:05 PM weckert Grating cover is mounted 1/4/01 2:14:18 PM gandreon Modification are needed. Back to assigned status. 1/11/01 1:43:01 PM gandreon Nearly ready... 2/1/01 1:58:37 PM gandreon To be finished next week. 2/8/01 2:39:04 PM gandreon To be finished by end of April. 5/3/01 2:38:19 PM gandreon To be completed next week. 5/10/01 3:03:59 PM gandreon The tube is installed. The grating protection still missing (low priority). 6/1/01 9:33:12 AM gandreon To be completed this week. 6/14/01 3:04:22 PM gihle To be accepted by the team and optician. 7/12/01 3:13:12 PM gandreon Alain should check it for possible vignetting. 8/16/01 3:03:22 PM gandreon Next Alain's turno. Responsible : Mechanics Support Team Status : Completed Deadline : 10/26/00 10:00:00 PM Deadline Status : Overdue ________________________________________________________________________________ Telescope : ESO 360 Create-date : 4/19/01 3:05:05 PM Problem Short Description : Broken pipes cause flooding of instrument. Action : Some sort of device to stop the water flux should be devised. Action Log : 5/3/01 2:40:02 PM gandreon Three special valves has been ordered. 6/1/01 9:40:18 AM gandreon Delivery is very late. GIH should check with C&P. 6/11/01 8:53:43 AM gihle The delivery has been confirmed by the 20th of June. However, the existing valve of a cooler that is not used was removed and installed in the 3.6m cooler. This together with a calibrated presostat that cut the system to prevent water flow were tested. The actual equipment will have the following characteristics : - In case that the circuit is obstructed, due to a non connected connector the valve will deviate the flow in bypass, preventing any possibility of a broken line or connection. - If a line is cut the presostat will cut the system. The maximum amount of water that can be spilled is 190cc - The equipment has to pumps that allows water flows of 0.5 lt/min to 3.3 lts/min and output pressures between 1.12 to 2.2 bar - The equipment for a proper functioning needs to be pressurized to 1 bar. 6/28/01 4:19:46 PM gandreon To be tested during next test time (8-12 July) 7/12/01 3:15:35 PM gandreon The new system, which have been modified, is not currently used because not accepted yet. The valves original foreseen have to be installed on the adapter before this point can be closed. 8/16/01 3:04:23 PM gandreon MKU claim that a written report was promised and never delivered. Back to assigned. Responsible : Mechanics Support Team Status : Assigned Deadline : 7/11/01 11:00:00 PM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO 360 Create-date : 4/19/01 3:10:55 PM Problem Short Description : Cable holder beneath GP carriage does not move smoothly. Action : Another linear bearing will be added and tested during daytime for functionality (including additional friction). Action Log : 4/26/01 2:38:34 PM gandreon WEC prepared a design. MKU would like to have it ready by end of month. 6/7/01 2:46:30 PM gandreon In the workshop. 6/14/01 3:05:14 PM gihle To be completed this turno. 6/28/01 4:20:47 PM gandreon To be commissioned during test time in July. 7/12/01 3:16:34 PM gandreon Final test to be performed when Efosc 2 is installed. 7/19/01 3:04:41 PM gandreon So far the new configuration worked fine. However, no real "commissioning" can be done. Responsible : Mechanics Support Team Status : Closed Deadline : 6/14/01 12:00:00 AM Deadline Status : Closed on Time ________________________________________________________________________________ Telescope : ESO 360 Create-date : 6/1/01 9:29:15 AM Problem Short Description : Sensors for the lateral position of M1 do not provide reliable readings. Action : They have to be repositioned far from the mirror edge. Action Log : 8/2/01 3:05:41 PM gandreon Parts are ready, but installation could not be done this time. To be done during next change-over. 8/9/01 4:49:39 PM gandreon To be installed next Monday. 8/10/01 3:37:04 PM gihle In agreement with the 3p6 Team the sensors are going to be installed next changeover (from EFOSC to CES) as the Monday one takes to long to add this extra work. 8/16/01 3:04:58 PM gandreon It will be done on August 25th. Responsible : Mechanics Support Team Status : Assigned Deadline : 7/31/01 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO 360 Create-date : 6/1/01 9:30:42 AM Problem Short Description : Electrovalves used for M1 force distribution loose their calibration. Action : A procedure for recalibration is needed. Action Log : 6/11/01 8:56:09 AM gihle A proposal to calibrate all the electrovalves is studied by SMC. They will send the offer as soon as possible. 6/14/01 3:07:17 PM gihle The offer of SMC is in our hands. A PR will follow next week. 6/28/01 4:30:00 PM gandreon PR has been issued. 7/1/01 2:43:15 PM gihle Due to Alainīs holidays and after his request, the calibration should be postponed to August 2001. I will contact SMC in order to organize the visit of their technician around the second week of August when Alain and Juan Fluxa are here. 7/12/01 3:19:06 PM gandreon Date set is August 2nd. Responsible : Mechanics Support Team Status : Closed Deadline : 7/15/01 12:00:00 AM Deadline Status : Closed on Time ________________________________________________________________________________ Telescope : ESO 360 Create-date : 7/10/01 12:39:51 PM Problem Short Description : F/35 top ring, removal structure problematic Action : Review the design of the F/35 top ring removal structure. It is very difficult to install and three to four hours are lost just in latching the frame into the top ring. This implies a late start up when Timmi is installed. Action Log : 7/26/01 3:01:52 PM gihle Some improvements were made. To be tested next changeover. Responsible : Mechanics Support Team Status : Closed Deadline : 7/18/01 11:00:00 PM Deadline Status : Closed on Time ________________________________________________________________________________ Telescope : ESO 360 Create-date : 7/11/01 12:51:55 PM Problem Short Description : No air pressure meter at the M1 air inlet, in the telescope. Action : Install a pressure meter to measure the air pressure. Maximum pressure above 7 bars. Action Log : 7/23/01 12:24:48 PM gihle There are two manometers to check air inlet pressure at the M1 unit. The first one is placed in the outer West side wall of the mirror cell. The second one is located at the air pressure controller in the cass. cage. This one monitor the air inlet pressure prior to the electrovalves regulation. Please clarify what is required. 8/9/01 4:50:37 PM gandreon A third manometer will be installed this week-end. 8/10/01 3:35:00 PM gihle The manometer has been installed. Responsible : Mechanics Support Team Status : Completed Deadline : 8/15/01 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO 360 Create-date : 7/12/01 3:11:13 PM Problem Short Description : Some TCS commands are operationally inefficient. Action : Add the following commands: - Stop current preset. - Preset telescope only to Zenith - Move Dome to parking position Action Log : 7/26/01 3:03:04 PM gihle IKA will analyse this problem after the 2.2m upgrade. 8/9/01 4:51:29 PM gandreon Tentative deadline assigned. 8/16/01 3:05:44 PM gandreon Only "Stop preset" still missing. 8/16/01 3:45:55 PM ikastine Comments of Victor Merino. He did not have write access. This action was assigned to vmerino. The old "Zenith" option was renamed as "Park" and works sending telescope and dome to park positions. A new option was added to e3p6guiTCS panel labeled "Zenith" which just move the telescope to the required position but the dome that remains in same position preseted. The stop preset must be installed/tested next week. Responsible : Software&Commun.Supp.T. Status : Assigned Deadline : 9/20/01 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO 360 Create-date : 7/19/01 2:56:09 PM Problem Short Description : Several DB points required for CES set-up are missing. Action : They should be added, possibly by August 15 (start of next run). Action Log : 7/26/01 11:41:57 AM jguzman OLDB point @wces:Appl_data:ces:SETUP created and installed in wces with the attributes listed in the e-mail sent by E.Barrios. Changes are ready to be tested by 3.60m team telescope. Responsible : Software&Commun.Supp.T. Status : Closed Deadline : 8/15/01 12:00:00 AM Deadline Status : Closed on Time ________________________________________________________________________________ Telescope : ESO 360 Create-date : 8/16/01 2:58:08 PM Problem Short Description : Lateral pads error messages in pop--up windows interfere with operations. Action : Messages should go to the TCS logging facility or to a stardard X-Trem window. Action Log : Responsible : Software&Commun.Supp.T. Status : Assigned Deadline : Deadline Status : Not Assigned ________________________________________________________________________________ Telescope : ESO/MPI 220 Create-date : 11/2/00 2:10:08 PM Problem Short Description : WFI filters are not qualified according to their optical quality. Action : Optical quality of all WFI filters should be measured. Action Log : 11/8/00 3:16:27 PM agilliot This action concerns two parts: - optical quality check of all WFI filter with point source focal reducer device to be implemented on the optics lab (a check of the tracking filter could be done) - improvement of all tracker filters by removing the spacer and installing a proper inclined shim to orientate better the filter with the out of axis beam. Time available to perform this time consuming operation could start in january Therefore the deadline must be around end of February at the earlest 11/9/00 2:25:06 PM gandreon First useful idle period is in January. A couple of periods required. 12/30/00 7:55:00 AM agilliot Optical bench to be prepared suring the second week of January 1/11/01 8:16:29 AM agilliot as scheduled the optical bench will be prepared during this turno 1/16/01 2:28:41 PM agilliot Optical bench ready . a first OIII filter was tested in parallel beam and found with large defoc !!!! more tests to be done next turnos ... pls 2p2team .... 4 filters will be done each days ..... starting next tuesday ... 1/25/01 9:16:09 AM agilliot as foreseen, three filters have been completed - IQ check (too are not good) - tracking filter improved (filter stack with high viscosity optical oil) the operation require almost the full day .... and the perspective of 4 filters per day seems ok .... 2/8/01 7:49:06 AM agilliot During this turno, 11 filters were characterized. It's at least represent a 1/3 of the available filters. Not only the ESO numbered filters are measured. On time for the end Of March 2/15/01 8:31:13 AM agilliot 12 new filters measured this short turno 2/28/01 8:22:16 PM agilliot New measure campgain on mid March 3/16/01 10:54:41 AM gihle 50% is done , however , so far 5 are not correct. This will be inmediately informed to the users. It was informed that also the guiding filters are improved. All this will come in a report 3/20/01 11:25:50 AM agilliot pre analysis of the images shown assymetry altready on the reference image . The bench setup had to be improved ............ using pinholes but then stray light level get too high .... and it is in phase to be improved by now no filter were measured ..... due to this point The deadline will have to be moved to finish the campaign in April during the down time .... with access to the allway use I filter 3/22/01 3:49:53 PM gandreon Urgent. Qualitative data already available to be transmitted to TT for immediate publication in the WEB. 4/19/01 3:00:23 PM gandreon Delivery may be delayed. 5/10/01 10:55:23 AM agilliot qualitative data delivered ..... requiring full moon period of WFI free of observer to complete action 5/10/01 3:06:18 PM gandreon New deadline set accordingly. 6/7/01 10:19:44 AM agilliot 13 filters measured ..... 4 are still scheduled for today to finish the verification. Several filters are bad and will be reported by email. The complete reduction of the data for a final report will require more time, after using IDL to be installed on line in the optical office 6/28/01 4:23:10 PM gandreon Dealine extended for the preparation of final report. 8/12/01 11:35:22 AM agilliot as informed previously the filters presenting an image degradation have been listed to the 2.2 team. The final report requires image analysis presentation which requires the installation of a new Linux Pc on the optical lab equipped with IDL., the recent facilities on image analysis as used by observers. Requests have been several time forwarded to the management. Some delays occured and the pc is now delivered but requiring the linux OS instalation as well as the IDL. Responsible : Instrumentation Support Team Status : Assigned Deadline : 9/19/01 11:00:00 PM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO/MPI 220 Create-date : 6/29/01 11:30:51 AM Problem Short Description : Feasibility study for rotating Grism at 2p2 telescope. Action : As discussed in the last LSMM (29 June), we would like to know the resources and time-scales involved to install a simple (manual!) rotation of the Grism (0 degrees and 90 degrees) with WFI at the 2p2. This modification might also possibly involve ISG and the Electronic Teams. Action Log : 7/5/01 2:46:46 PM gandreon There are design considerations to be clarified before this point can be assigned. It seems that the grism cannot be rotated without loosing the guiding capability. 7/12/01 3:20:17 PM gandreon The only solution is the rotation of the complete instrument. 7/22/01 9:43:00 AM gihle During the 2.2m upgrade the possibility to rotate the instrument was discussed and a project developed. The designed unit is installed, however the instrument arrived with an extra spacer flange that required to remove the main rotating drive gear from the telescopeīs rotator. To re-activate the unit (it has a motor and encoder), we will need to make a small modification to the instrumentīs extra spacer flange. To modify this spacer the instrument needs to be lowered and be out of the telescope for at least 2 nights. 8/2/01 3:32:05 PM gandreon TT: please define dates. 8/9/01 4:52:58 PM gandreon Test time available starting September 28th. To be coordinated with SWC that also need time. Responsible : Mechanics Support Team Status : Assigned Deadline : 9/30/01 11:00:00 PM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO/MPI 220 Create-date : 7/13/01 12:41:22 AM Problem Short Description : At night, light from the base can get into the platform and adversely affect observations if the lights are on. Action : We need to have a timer (15 minutes) for the lights at the base of the telescope. Action Log : 7/26/01 3:05:07 PM gihle Timer will have a 10 min delay and also a manual override of the automatic mode. Responsible : Infrastructure Support Group Status : Closed Deadline : 8/2/01 12:00:00 AM Deadline Status : Closed on Time ________________________________________________________________________________ Telescope : ESO/MPI 220 Create-date : 7/19/01 2:51:12 PM Problem Short Description : Few paramaters are missing in control panels for the use of grisms. Action : Grism parameters should be added to the OS panel and adapter angle to the TCS one. Action Log : Responsible : Software&Commun.Supp.T. Status : Assigned Deadline : 9/29/01 11:00:00 PM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO/MPI 220 Create-date : 8/9/01 4:45:07 PM Problem Short Description : Need to build new V filter for WFI tracker chip. Action : The images porduced by the current V filter on the tracker chip are elongated, causing bad guiding. According to Alain this could be solved by a better new V filter, which he can manufacture with glass available on his workshop. Action Log : Responsible : Instrumentation Support Team Status : Assigned Deadline : Deadline Status : Not Assigned ________________________________________________________________________________ Telescope : ESO 152 Create-date : 7/6/01 4:28:11 PM Problem Short Description : Lower wind screen needs complete overhaul. Action : The lower windscreen at the ESO1.52 needs a complete overhaul. The screen has gotten stuck several times, and when it works its motion is really slow. The drive motor should also be ckecked. Because of the long tube, this telescope is prone to oscillations if wind is not properly shielded. Upper windscreen should be serviced as well. Action Log : 7/26/01 3:07:51 PM gihle The windscreen was repaired. However the complete overhaul is required. Due to training course both dome mechanics are going to be out of La SIlla next week. Deadline to be changed. 8/2/01 3:35:40 PM gandreon Dome mechanic to be contracted after accident to O Varas. Responsible : Mechanics Support Team Status : Assigned Deadline : 8/1/01 11:00:00 PM Deadline Status : Pending ________________________________________________________________________________ Telescope : ESO 152 Create-date : 7/6/01 4:31:38 PM Problem Short Description : Telescope tube needs painting. Action : The telescope tube needs proper painting. There are many scrathes in the tube, and the general appearance of the telescope is bad. The tube, polar axis, counter-weight arm and counter wight should all be painted. Action Log : 7/26/01 3:08:39 PM gihle The go ahead of this point requires the acceptance of the Director. 8/9/01 4:54:27 PM gandreon Deadline set for the first part, to be started on September 16th. 8/16/01 3:06:48 PM gandreon Against planning, painting is going to start now. Responsible : Infrastructure Support Group Status : Assigned Deadline : 9/20/01 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : GENERAL Create-date : 7/26/01 3:11:02 PM Problem Short Description : The anodizing plant floor in the Astroworkshop is in poor conditions due to acid attack. Action : To repair and to paint the roomīs floor with special resistant paint. Action Log : Responsible : Infrastructure Support Group Status : Assigned Deadline : 8/20/01 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : GENERAL Create-date : 7/31/01 12:54:46 PM Problem Short Description : Extension of cooling circuit for Technical CCDs Lab Action : A new set of water pipes/hoses are needed in the new dark room of the CCD Lab. for cooling Technical CCDs or Fiera systems using the present water chiller we have. This is needed by end of August. Action Log : 8/2/01 3:34:17 PM gandreon To be decided after the constitution of the engineering department. Responsible : Mechanics Support Team Status : Assigned Deadline : 8/23/01 12:00:00 AM Deadline Status : Pending ________________________________________________________________________________ Telescope : GENERAL Create-date : 8/2/01 3:11:34 PM Problem Short Description : Digital clocks on the mountain are not synchronized. Action : All clocks (UT,ST, online computers clocks) should be synchronized. Action Log : Responsible : Electronics Support Team Status : Assigned Deadline : Deadline Status : Not Assigned ________________________________________________________________________________ Telescope : GENERAL Create-date : 8/5/01 4:53:11 PM Problem Short Description : New version of scisoft (July 2001) needs to be installed. Action : Please install and configure the latest version of scisoft (July 2001) on drl6, w2p2off, and on the new linux reduction box for the 2p2. The current version of scisoft on drl6 is Nov. 2000. Action Log : 8/16/01 3:08:02 PM gandreon A bug has been discovered. HQ has been notified. Waiting for solution. Responsible : Software&Commun.Supp.T. Status : Assigned Deadline : Deadline Status : Not Assigned ________________________________________________________________________________