ACTION ITEMS LIST FOR SUPPORT TEAMS AND LOGISTIC ------------------------------------------------ Week 19/97: May 7 - May 13, 1997 --------------------------------------- Attendance: S Benetti, J Storm, T Augusteijn, G Ihle, G Lundqvist, W Eckert, A Gilliotte, J Melnick, U Weilenmann, G Andreoni, R Medina, P Sinclaire. A. NTT T 96.35.01 COVER FOR TRANSPORT OF PRIMARY MIRROR TO COATING PLANT IS INADEQUATE ACTION: Either it will be modified or a new one has to be manufactured before next aluminization. Responsible: G Ihle Deadline: June 97 T 97.10.01 WASHING OF PRIMARY MIRROR NEEDS TO BE PREPARED Action: Few pieces have been machined. One N2 bottle should be made available. Responsible: G Ihle Deadline: May 20 (Washing is planned on 21) T 97.10.02 ENCODER LAMP WILL BE REPLACED ON RB AND AZ Action: support from mechanics is required to carry out the operation. Responsible: G Ihle Deadline: Period 13-20 May. I 97.10.03 WATER IS REQUIRED FOR MIRROR WASHING Action: A temporary installation should be provided at the telescope floor. Responsible: L Aguila Deadline: May 20 T 97.18.01 PLATE FOR EMMI ALIGNMENT IS REQUIRED Action: the plate, with some 18 holes 60 microns each, has been delivered. Responsible: G Ihle Deadline: May 5 CLOSED 97.18 B. 3.6 T 96.12.01 ADONIS INSTALLATION IN CASSEGRAIN NEEDS IMPROVEMENTS ACTION: The interconnection between the two racks and the optical bench should be rewired. Ruggedized connectors should be ordered and installed (possibly VLT compliant). It is now under the responsibility of the 360 Tel.Team. Responsible: Now: 360CAT TT Deadline (new): end of June 97(after reformulation of the point) CLOSED 97.19 T 97.12.02 SHELL SCRIPT NEEDED TO RUN IDL INTERFACE FOR TIMMY Action: it has been written under guidance of IR team. Responsible: G Lundqvist Deadline: End of June CLOSED 97.19 T 97.17.01 VIBRATIONS ARE DETECTED WITH CES Action: The power spectrum should be measured in order to identify sources. Accelerometers should be used to find where there is a shortcut between building and coude' platform. Responsible: A Gilliotte Deadline: End of June T 97.17.02 F80 TELESCOPE IN ADONIS NEEDS ADJUSTMENT DEVICE Action: a simple device (a screw without micrometer) has been added. Responsible: G Ihle Deadline: May 10 CLOSED 97.19 T 97.17.03 SUPPORT IS NEEDED FOR THE VME USED BY DIRECT IMAGING Action: a suitable plate should be prepared. Responsible: G Ihle Deadline: End of June T 97.17.04 ADONIS COVER NEEDS FIXATIONS Action: magnetic fixations should be added. Responsible: W Eckert Deadline: September 1 T 97.19.01 FILTER LIST FOR SHARP SHOULD BE UPDATED Action: the control program should be modified in order to include the narrow band filter already installed in Sharp. Responsible: U Weilenmann Deadline: End of May F. CAT/CES T 97.18.01 ANOTHER IRS COPY IS NEEDED FOR CONCURRENT INSTRUMENT TEST Action: it has been installed. To be tested. Responsible: G Lundqvist Deadline: End of May C. 2.2m T 97.15.01 NEW BATCH NEEDED FOR IRAC I Action: To be adapted from existing one. Responsible: G Lundqvist Deadline: End of May. D. D1.5m T 97.14.01 BIAS PROGRAM FOR NEW CCD HAS DIFFERENT INTERFACE Action: Daisy has been modified in order to permit increased read-out mode. Responsible: G Lundqvist Deadline: Mid May CLOSED 97.19 E. E1.5m T 97.19.01 FORMULA FOR SLIT SIZE DOES NOT INCLUDE OFFSET Action: The zero point should be added in the control program by Flavio. Responsible: G Lundqvist Deadline: End of May T 97.19.02 ECHELEC SHOULD BE REMOVED FROM COUDE' ROOM Action: To be done. Responsible: A Gilliotte Deadline: End of June G. 1m H. 0.9m Dutch T 97.11.01 IMAGE TRANSMISSION FAILS ONCE IN A WHILE Action: Eduardo should provide the TT with instructions for the monitoring and troubleshooting of the problem. The same happens at the Danish. Responsible: G Lundqvist Deadline: End of March. I. 0.5m ESO J. 0.5m Danish K. Schmidt L. SEEING Monitor M. MIDAS N. SEST T 97.17.01 THE FRONT PANEL FOR THE TCS IS NEEDED Action: it has been machined. Responsible: G Ihle Deadline: May 9. CLOSED 97.18 O. MARLY EROS2 (formerly GPO) W. CCD detectors. Z. General. T 97.10.01 PLASTIC HOSES IN GLYCOL MANUAL PUMPS SHOULD BE REPLACED Action: a permanent installation should be done at 2.20 and 3.60. Responsible: G Ihle (CHANGED) Deadline: End of September ACTION POINT STATISTICS YEAR 1997: Opened Closed Total Pending Opened Week 1/97 4 1 1 17 Week 2 7 3 8 21 Week 3 1 3 9 19 Week 4 1 2 10 18 Week 5 0 0 10 18 Week 6 1 2 11 17 Week 7 0 5 11 12 Week 8 1 0 12 13 Week 9 4 6 16 11 Week 10 4 1 20 14 Week 11 3 0 23 17 Week 12 7 0 30 24 Week 13 0 4 30 20 Week 14 2 1 32 21 Week 15 2 5 34 18 Week 16 0 3 34 15 Week 17 5 5 39 15 Week 18 2 2 41 15 Week 19 3 4 44 14