Version: 1.1 2002-11-25 J.D.Pritchard

Highlights of the Relocation and Installation of FEROS to the ESO/MPI 2.2m telescope

Disassembly, Relocation and Re-Assembly & Alignment -- October 6 - 11, 2002

The Disassembly, Relocation and Re-Assembly & Alignment was completed as planned and in quick time with no problems. Furthermore as a result of the realignment, the instrument is possibly in better shape than prior to the move.
During alignment tests the shutter was noticed to be malfunctioning. A modification to the release cable by A.Kaufer remedied the problem.
Disassembly, Relocation and Re-Assembly & Alignment was lead by A.Kaufer and assisted by A.Gilliotte, I.Saviane, J.Pritchard, G.Ihle and a large team from MEC.
More details to come...

FEROS/WFI Adapter and Calibration Unit Installation -- October 16 - 22, 2002

Final Opto-Mechnical/Electronic integration, testing and alignment included:
More details to come...

FEROS/WFI Adapter and Calibration Unit Modifications -- October 27-November 13, 2002

The following modifications were made to the FEROS/WFI Adatper and Calibration Unit during the period October 27 to November 13, 2002: